Hi neighbors! We received this letter as an update from the City of St. Paul on the roadway construction for Franklin. We’re sharing it here:
This letter is to inform you of upcoming roadway construction for the Franklin Avenue Paving Project. Throughout the construction process, portions –if not all– of this roadway will be closed and possible detours set-up. Please see the attached map for the project location.
Roadway construction is expected to begin on approximately August 31st.
The contractor for this project is Bituminous Roadways, Inc., 1520 Commerce Drive, Mendota Heights, MN 55120, 651-686-7001.
If you have questions you may contact me at 651-266-6155, Scott Brimer the project supervisor at 651-266-6225, or our on-site inspector Steve Herbert at (cell) 651-755-5985 (office) 651-266-6027. Steve is in contact with the project contractors on a daily basis, and is most up-to-date on current project information.
Thank you,
Jessee Farrell
Project Engineer